Genesee 4 & 5

Alberta, Canada

Status

In Development

Proposed Capacity

530*

MW

Natural Gas
Status
In Development
OWNED CAPACITY

530*

MW

Natural Gas

The proposed 1,060 MW Genesee 4 and 5 combined cycle natural gas-fired generation facility is a joint venture project between Capital Power and ENMAX. Its planned location is entirely within the boundaries of the existing Genesee Generating Station, 70 kilometers west of Edmonton. Capital Power will lead the development and construction of the project and subsequently be the operator. The agreements include an eight-year tolling arrangement under which ENMAX will purchase 50% of Capital Power’s share of the facility’s output for eight years. The project has received all regulatory approvals required from the Alberta Utilities Commission (AUC) and Alberta Environment and Parks (AEP, formerly Alberta Environment and Sustainable Resource Development).

*1,060 MW planned facility jointly owned with ENMAX

Quick Facts

  • Construction will be in two phases, with the first phase expected to take 3 years and the second phase taking an additional year to complete
  • On-site construction will create approximately 1,200 person-years of employment with about 850 people working on the project at its peak
  • Once operational, the facility will employee 25 to 30 full-time staff
  • Expected life of the natural-gas fired facility is 35 years
  • The facility will feature the world’s most advanced J-series natural gas turbine technology commercially available with approximately 4% less CO2 and NOx emissions and superior flexibility to respond to sudden fluctuations in supply and demand

 

Capital Power and ENMAX continue to assess the timeframe for starting work on this project. Continuation and timing of the project will be further considered when new generation is required to balance supply and demand. Capital Power submitted an application for a time extension to complete construction of Genesee 4 and 5 to the Alberta Utilities Commission (AUC) and requested that the approved construction completion date of December 31, 2018 be amended to March 31, 2022 for Unit 4 and from December 31, 2018 to March 31, 2023 for Unit 5. The AUC approved this application on December 11, 2018.  With the project’s flexible two-phase construction and staged completion, and commercial agreements with flexibility on the timing of the in-service date for the project to be timed to correspond to the need for new power generation in the Alberta market, we are well positioned to complete the project before the end of the decade when nearly 1,000 MW of coal generation is scheduled to retire.

State-of-the-Art Technology

Agreements have been finalized with Mitsubishi Hitachi Power Systems for the supply and maintenance of the world’s most advanced J-series natural gas turbine technology commercially available. The facility will have a nominal generation capacity of 1,060 MW consisting of two 530 MW units. The facility will consist of two one-on-one, single shaft power islands, each incorporating a 501 J-class natural gas turbine, steam turbine, generator and heat recovery steam generator. This technology has a lower heat rate than previous technology resulting in higher efficiency and about a four per cent reduction in CO2 and NOx emissions compared to the previous generation’s technology. The J-class technology also provides superior flexibility to respond to sudden fluctuations in supply and demand and is the cleanest and most efficient thermal power generating system that complements renewable energy sources, making it well suited for the Alberta power market.

The proposed construction of Genesee 4 and 5 supports Capital Power’s growth, and sustainability initiatives in many ways. The project will be one of Alberta’s most advanced generation facilities and will feature a number of environmental attributes, designed to meet the province’s air emission standards and performance expectations.

Consultation and Engagement

We value and consider local community interests and priorities. We engage government, employees, local communities, investors, shareholders, and Indigenous communities. Our goal for every project, every facility and every initiative, internal and external, is to build, operate, and align with the interests and priorities of those closest to, and most impacted by, our operations.

Site Contact

What's New

Media Releases
Capital Power announces date for release of its first quarter 2020 financial results and analyst conference call

Capital Power will release its first quarter 2020 results before the markets open on May 4, 2020. Management will host a conference call with analysts on the same day at 9:00 a.m. MT (11:00 a.m. ET...

Media Releases
Capital Power completes acquisition of Buckthorn Wind and receives tax equity financing for Cardinal Point Wind

Capital Power announced today that it has successfully completed the acquisition of Buckthorn Wind from private investors. Buckthorn Wind is a 100.5 megawatt wind facility that is located in Erath ...

News and Stories
Message from Brian Vaasjo, CEO and President

Capital Power's Response to COVID-19: A Message from Brian Vaasjo, CEO and President

Media Releases
Capital Power adds 250 megawatts of long-term contracted wind generation to its renewable portfolio

Capital Power announced today that it has entered into an agreement to acquire a 100% ownership interest in Buckthorn Wind, a 100.5 megawatt wind facility, from private investors.

Media Releases
Capital Power named one of the 2020 World’s Most Ethical Companies® by Ethisphere
Second recognition highlights company’s leadership on ethics and compliance practices

Capital Power has been recognized by the Ethisphere Institute, a global leader in defining and advancing the standards of ethical business practices, as one of the 2020 World’s Most Ethical Compani...

News and Stories
Powering a Resilient Future: 2019 Climate Change Disclosure Report

Our 2019 Climate Change Disclosure Report, aligned with the Task Force on Climate-related Financial Disclosures (TCFD) recommendations, discusses our governance, processes and strategies for addres...

Media Releases
Capital Power reports excellent fourth quarter and year-end 2019 results
Excellent year highlighted by record cash flow generation

Capital Power today released its financial results for the quarter ended December 31, 2019. Results outline excellent year highlighted by record cash flow generation.

Media Releases
Capital Power Announces Brian Vaasjo to Remain President and Chief Executive Officer

The Board of Directors of Capital Power is pleased to announce that Brian Vaasjo will remain as President and Chief Executive Officer of the Company.

Media Releases
Capital Power announces approval of normal course issuer bid for purchase of up to 10.5 million of its common shares

The Toronto Stock Exchange (TSX) has approved Capital Power Corporation's ("Capital Power" or "the Company") (TSX: CPX) normal course issuer bid ("NCIB") to purchase and cancel up to 10,513,532 of ...

Media Releases
Capital Power declares dividends for its Common and Preference shares

The Board of Directors for Capital Power Corporation (TSX: CPX) (Capital Power) declared a dividend of $0.48 per share on the outstanding common shares for the quarter ending March 31, 2020. The di...